 OVERVIEW -------- 
 TOBA MONTROSE UPDATE -------------------- 
 - 93% completion of the engineering, procurement and construction ("EPC") contract - Completed work includes the transmission line, East Toba powerhouse, penstock and intake - Ongoing work includes commissioning of East Toba plant, and completion of Montrose powerhouse, penstock and intake 
 DOKIE WIND PROJECT UPDATE ------------------------- 
 2010 UPDATES AND FORECASTS -------------------------- 
 FINANCIAL RESULTS ----------------- 